I think everything is in place for inflating the air form. The slab is set, we got a new security gate installed today to help secure the property over night, the water is connected dire tly adjacent to the dome, and the electrical is set up. There is even one of the fans used to inflzte the dome on site. All we need now is a date scheduled by Monolithic. I hope to get that date by tomorrow and we can publicize it widely. It will probably be early next week if I were a betting man. This week is the last week of the spring workshops at Monolithic, so most of their people are tied up with that.