Thursday, April 19, 2012

Day two of slab work complete

I don't have a photo for today, but I do have a nifty table to summarize the expected progress of building the slab. This is just an estimate and things may certainly shift by a few days depending on things like the weather and whatnot, but it is a fairly good estimate.

4/17/2012
4/20/2012
Break Ground, initial phase of digging the beams and building the frame
4/23/2012
4/25/2012
Plumbing and electrical in the slab
4/26/2012
5/1/2012
Complete frame, lay rebar, prepare to pour
5/2/2012
5/3/2012
Pour Slab
5/5/2012
Inflate the Airform

We also got the inspection for the power pole and setup, so in the next few days the utility company will be connecting our power and then the contractor will run a 320 amp circuit from the utility pole up to the job site (about 200 feet). He will also be running water up to the job site in the near future, since the water meters were installed recently.

All in all things are really starting to happen. The next few weeks will be exciting as stuff visually begins to happen around the job site.

No comments:

Post a Comment

Note: Only a member of this blog may post a comment.